How long does a kitchen remodel take? Once demolition starts, a full kitchen remodel usually needs 6 to 12 weeks of construction, according to Block Renovation's kitchen timeline guide. Counting design, contractor selection, permits and cabinet orders, the whole project often stretches to four to six months. Angi gives a similar picture: six weeks to four months for most homes, and longer when the layout changes.
The kitchen is the room where the calendar depends most on things that happen off site. Cabinets are built or shipped to order, stone counters are cut only after the boxes are installed, and every change to plumbing, gas or wiring needs a permit and an inspection. Knowing where those waiting periods fall makes the schedule far easier to plan around.
Planning a kitchen remodel in Boca Raton? Share the changes you have in mind and get a free, detailed estimate before anything is ordered.
How Long Does a Kitchen Remodel Take From First Idea to Final Walkthrough?
From the first idea to the final walkthrough, a full kitchen remodel commonly takes four to six months. Block Renovation, in its guide published April 1, 2025, describes about six months end to end for a typical project, with roughly two to three months of that spent planning before any cabinet comes off the wall.
The same guide breaks the early work into steps: 2 to 4 weeks of pre-renovation planning, 1 to 3 weeks to choose a contractor, 2 to 6 weeks of design development, and 2 to 4 weeks for permits and material orders. Those steps overlap in many projects, but together they explain why a kitchen that takes eight weeks to build can still occupy most of a year on your calendar.
Angi's kitchen remodel guide makes the same point from the other side. For larger projects, it estimates five to eight months from planning to post-construction cleanup, because more scope means more decisions, more orders and more inspections.
Kitchen Remodel Timeline by Type of Project
Scope is the single biggest factor in how long does a kitchen remodel take. A kitchen that keeps its footprint moves much faster than one where the sink, range or walls change position.
| Project | Scope | Construction time |
|---|---|---|
| Cosmetic refresh | Paint, new hardware, lighting fixtures, new counters on existing cabinets | About 1 to 3 weeks |
| Mid-range remodel, same layout | New stock or semi-custom cabinets, counters, backsplash, flooring, appliances | About 6 to 8 weeks |
| Full remodel with new layout | Moved sink or range, removed wall, new circuits, custom cabinets | About 8 to 12 weeks or more |
Sources: Block Renovation, How Long Does a Kitchen Remodel Take?, April 1, 2025 (6 to 12 weeks of construction for a full kitchen); Angi, kitchen remodel timeline guide, retrieved November 10, 2026. These are general ranges, not a price or schedule for any particular kitchen.
The table is a starting point. Two kitchens of the same size can land at opposite ends of a range because one uses in-stock cabinets and the other waits on a custom order.
What Happens in Each Phase of a Kitchen Remodel?
A kitchen remodel moves in a fixed order, since every trade waits on the previous one. Block Renovation lists these construction phases and durations:
- Demolition. Old cabinets, counters and flooring come out in about 1 to 5 days.
- Rough construction and trades. Framing changes, plumbing, gas and electrical rough-in take about 1 to 3 weeks.
- Rough inspections. The building department checks the work inside the open walls before they are closed.
- Installation and build-out. Cabinets, counters, flooring, backsplash, lighting and appliances go in over about 2 to 4 weeks.
- Finishing touches. Paint, trim, hardware, the punch list and cleaning take about 1 to 2 weeks.
- Final inspection. The building department closes the permit, and you walk through the finished room.
Block Renovation also recommends adding a 10 to 20 percent buffer to both the schedule and the budget, since a kitchen has more trades and more deliveries than almost any other room.
How Long Do Cabinets and Countertops Take?
Cabinets and countertops are usually the longest waits in the whole project, and they happen in sequence, not at the same time. If you are asking how long does a kitchen remodel take with custom cabinets, the order date matters more than the install date.
Cabinets. Kitchen Cabinet Kings, in a July 2026 article on lead times, lists 1 to 2 weeks for stock or quick-ship cabinets, 4 to 6 weeks for semi-custom lines and 6 to 12 weeks for custom builds, with spring and holiday periods adding time. Block Renovation cites 8 to 12 weeks for custom cabinetry. Because of that wait, cabinets are normally ordered as soon as the design is final, often before demolition.
Countertops. Stone and quartz counters are measured only after the cabinets are installed and level. Slabwise's countertop installation guide, updated July 10, 2026, puts the template visit at 1 to 2 hours, fabrication at 7 to 14 days after the template, and the installation itself at 3 to 6 hours for a typical kitchen. It adds 1 to 3 weeks when the slab is a special order, and notes that busy shops can carry a 2 to 3 week queue between March and September.
That sequence means many kitchens spend one to three weeks with new cabinets but no counters and no working sink. Planning for that gap early saves a lot of frustration.
Do You Need a Permit for a Kitchen Remodel in Florida?
In Florida, a kitchen remodel that changes plumbing, gas lines, electrical circuits or walls generally requires a building permit and inspections under the Florida Building Code. Replacing a countertop on existing cabinets, or painting, usually does not. Your licensed contractor applies for the permits and schedules the inspections the work needs.
State law sets an outside limit on the review. Section 553.792 of the Florida Statutes gives local building departments up to 30 business days to approve, approve with conditions or deny a complete application for a residential project under 7,500 square feet. Many kitchen permits are issued faster, but that ceiling is useful when you build a schedule.
Inspections add their own steps. A remodel with new circuits and moved plumbing typically needs rough inspections before drywall and a final inspection at the end, and each visit depends on the building department's calendar. In a condominium or a community with an HOA, approval from the association may be required before work begins as well.
What Can Delay a Kitchen Remodel?
Most delays come from orders and decisions, not from the work itself. Ask any contractor how long does a kitchen remodel take, and a good answer always includes what could push it back.
Late or wrong deliveries
A cabinet box that arrives damaged or a missing filler panel can stop installation for days or weeks, because the countertop template cannot happen until every cabinet is set. Checking each delivery against the order the day it arrives catches problems early.
Changes after the template
Slabwise notes that changing the edge profile, adding a sink cutout or switching material after the template restarts fabrication. The same applies to swapping an appliance size once the cabinets are built around it.
What is hidden behind the walls
Opening walls in an older kitchen can reveal outdated wiring, corroded supply lines or framing that has to be corrected to meet current code. Each discovery adds work and, often, another inspection.
Peak-season backlogs
Remodeling demand peaks from late winter through summer. Cabinet makers and stone fabricators both run longer queues in those months, so ordering early matters more.
Remodeling a kitchen in West Palm Beach? Get a free, detailed estimate with the scope and the order of work written out.
How Do You Live Without a Kitchen During the Remodel?
Most families keep living at home during a kitchen remodel, so a temporary kitchen makes the weeks much easier.
- Set up a small station elsewhere. A table in the dining room or garage with the refrigerator, a microwave, a coffee maker and an electric burner covers most daily meals.
- Plan for dishes. With no kitchen sink, paper plates or a laundry or bathroom sink for washing become part of the routine.
- Pack by use. Keep a few pots, utensils and staples in an accessible box and store the rest out of the work area.
- Expect dust and noise. Demolition and rough-in are the loudest weeks; installation days are quieter but busy.
- Ask about the sink gap. Knowing when the counters, sink and faucet are scheduled helps you plan those weeks without a working sink.
How to Plan Around Your Kitchen Remodel Timeline
The fastest kitchen remodels are the ones where every decision is made before anything is torn out. The answer to how long does a kitchen remodel take is largely set during planning.
- Finish the design first. Cabinet layout, appliance sizes and the sink location should be fixed before ordering.
- Order long-lead items early. Cabinets, special-order slabs and appliances should be confirmed before demolition starts.
- Ask for a written estimate and schedule. A detailed estimate lists the scope, the materials and the order of the trades.
- Confirm who handles permits. The contractor should pull the permits and coordinate every inspection.
- Build in a buffer. Leave room for one late delivery or one extra inspection.
- Plan the bathroom separately if needed. If both rooms are on the list, our guide on how long a bathroom remodel takes shows how the two schedules compare.
How AE Pro Builder Handles Kitchen Remodels
AE Pro Builder holds Florida Certified General Contractor license CGC1537851. The company was founded by Andre de Paula, who has worked in construction since 2018. Each kitchen project begins with an itemized estimate covering scope, materials and sequence, and AE Pro Builder handles the permit applications and inspections.
While the work is underway, you get updates as each phase wraps up, with one person to call from demolition to the final inspection. AE Pro Builder remodels kitchens in Boca Raton, Delray Beach and West Palm Beach.
Want a timeline for your kitchen? Reach us at (754) 271-8338 or ask for a free estimate through our page on kitchen remodeling in Boca Raton.
Frequently Asked Questions
What is the typical construction time for a full kitchen remodel?
A full kitchen remodel usually needs 6 to 12 weeks of construction, according to Block Renovation. With planning, permits and cabinet orders, the whole project often takes four to six months.
Can a kitchen be remodeled in two weeks?
A cosmetic refresh, such as paint, hardware, lighting and new counters on existing cabinets, can be finished in about one to three weeks. A remodel with new cabinets, moved plumbing or new circuits takes longer because of orders, permits and inspections.
Why does the countertop take so long after the cabinets?
Stone and quartz counters are measured only after the cabinets are installed and level. Fabrication then takes about 7 to 14 days, according to Slabwise, and longer for special-order slabs or during busy months.
How long does a kitchen remodel permit take in Florida?
Timing varies by city and county. Under section 553.792 of the Florida Statutes, the building department has a maximum of 30 business days to decide on a complete residential permit application for a home smaller than 7,500 square feet, and many kitchen permits come back sooner.
Conclusion: How Long Does a Kitchen Remodel Take?
How long does a kitchen remodel take? Most full projects need 6 to 12 weeks of construction and four to six months overall. The schedule depends less on the crew than on decisions, orders and inspections.
- Construction usually runs 6 to 12 weeks for a full kitchen.
- Start to finish, plan on four to six months, and more for custom cabinets or a new layout.
- Cabinets take from 1 to 2 weeks (stock) to 6 to 12 weeks (custom).
- Counters are fabricated in about 7 to 14 days after the template.
- In Florida, permits and inspections apply to most remodels that change plumbing, gas or wiring.
Ready to plan your kitchen? Call (754) 271-8338 to talk it through, or start with a free, detailed estimate for kitchen remodeling in Boca Raton.
Ready to plan your project?
Tell us what you want to remodel and get a free, detailed estimate from AE Pro Builder.
Get a Free Estimate
Tell us about your project and AE Pro Builder will prepare a free, detailed estimate.